    This topic has been deleted. Only users with topic management privileges can see it.
    • scottalanmillerS
      scottalanmiller @ntoxicator
      last edited by

      @ntoxicator said:

      Then its the though, Ok... then why not go with a packaged solution such as HC Scale.

      I think that those are really the only two major good options... something like XenServer plus HA-Lizard that you support yourself or get third party support for (like from @ntg) or going with a full packaged HC product that does all of this for you and you get inclusive support.

      1 Reply Last reply Reply Quote 0
      • scottalanmillerS
        scottalanmiller @Dashrender
        last edited by

        @Dashrender said:

        Why are you comparing high end Oracle servers to low end HP/Dell? or are you saying that all HP/Dell are low end compared to Oracle? and if that is what you are saying, what make Oracle so much better? All all the leads solid gold? (kidding on that of course)

        Oracle, HP, Dell, Fujitsu are all on parity. Cisco and SuperMicro is a bit lower, but still quite good (Cisco has questionable value, SM has good value.)

        1 Reply Last reply Reply Quote 0
        • scottalanmillerS
          scottalanmiller @ntoxicator
          last edited by

          @ntoxicator said:

          LENOVO & the Lenovo IBM Server X were thecheapest so far

          So is slapping a whitebox desktop in there. Still crazy 😉

          1 Reply Last reply Reply Quote 0
          • ntoxicatorN
            ntoxicator
            last edited by

            Thanks everyone for continued input 🙂

            Lenovo & Sever X are now off the list and will not be mentioned again or brought up for pricing.

            I can re-provision these NAS units for back-up targets as suggested. Keep what is already here and then spend the money to do HA-setup using localized storage on the nodes

            Its getting the CEO to pull bandaid off and spend some $$. We generate plenty in gross revenue and plenty to spare for net profit. 50 grand worth of new equipment I think would not be all that bad considering it can left in production for probably 4+ years

            AconboyA coliverC 2 Replies Last reply Reply Quote 0
            • AconboyA
              Aconboy @ntoxicator
              last edited by

              @ntoxicator - for that kind of money, I could put in a cluster at the primary site, and cluster at a DR site, and have real time replication with failover and failback (and likely still have beer money left over).

              ntoxicatorN 1 Reply Last reply Reply Quote 1
              • ntoxicatorN
                ntoxicator @Aconboy
                last edited by

                @Aconboy

                Cool! 🙂 Would this be HC-Scale you're talking?

                AconboyA 1 Reply Last reply Reply Quote 0
                • AconboyA
                  Aconboy @ntoxicator
                  last edited by

                  @ntoxicator yup. Straight list on a 2000 series 3 node cluster (before discounting) is ~35k, and a 1000 series is ~25k.... not hard to get there at all.

                  ntoxicatorN 1 Reply Last reply Reply Quote 0
                  • coliverC
                    coliver @ntoxicator
                    last edited by

                    @ntoxicator said:

                    Thanks everyone for continued input 🙂

                    Lenovo & Sever X are now off the list and will not be mentioned again or brought up for pricing.

                    I can re-provision these NAS units for back-up targets as suggested. Keep what is already here and then spend the money to do HA-setup using localized storage on the nodes

                    Its getting the CEO to pull bandaid off and spend some $$. We generate plenty in gross revenue and plenty to spare for net profit. 50 grand worth of new equipment I think would not be all that bad considering it can left in production for probably 4+ years

                    Holy crap $50K? I wish I had that kind of budget in the past!

                    DashrenderD ntoxicatorN 2 Replies Last reply Reply Quote 1
                    • ntoxicatorN
                      ntoxicator @Aconboy
                      last edited by

                      @Aconboy - nice!

                      I thought was going to be more than that..... next week lets maybe get together for webinar and review. like to see the entire rundown

                      also there any documentation on migrating from XenServer VM to HC scale? Or does it support the same disk image

                      AconboyA 1 Reply Last reply Reply Quote 0
                      • DashrenderD
                        Dashrender
                        last edited by

                        While a Scale solution would be awesome... it just seems like overkill.

                        But if HA is really that important to the CEO, he has little choice I suppose.

                        1 Reply Last reply Reply Quote 0
                        • DashrenderD
                          Dashrender @coliver
                          last edited by

                          @coliver said:

                          Holy crap $50K? I wish I had that kind of budget in the past!

                          Where's my 1 Million likes button?

                          1 Reply Last reply Reply Quote 1
                          • AconboyA
                            Aconboy @ntoxicator
                            last edited by

                            @ntoxicator I can directly import .qcow2 images. Where are you located in the country and I will have a guy ping you directly

                            ntoxicatorN 1 Reply Last reply Reply Quote 0
                            • ntoxicatorN
                              ntoxicator @coliver
                              last edited by

                              @coliver

                              I'm anticipating 50k budget. Considering the millions of dollars we're grossing. They made comment of wanting something that will hold out until 2018 or so. To support ~300-400 employee's

                              JaredBuschJ scottalanmillerS 2 Replies Last reply Reply Quote 1
                              • ntoxicatorN
                                ntoxicator @Aconboy
                                last edited by

                                @Aconboy - East Coast.... Florida

                                AconboyA 1 Reply Last reply Reply Quote 0
                                • JaredBuschJ
                                  JaredBusch @ntoxicator
                                  last edited by

                                  @ntoxicator said:

                                  @coliver

                                  I'm anticipating 50k budget. Considering the millions of dollars we're grossing. They made comment of wanting something that will hold out until 2018 or so. To support ~300-400 employee's

                                  Then just do what we all told you to do and buy Scale gear.

                                  1 Reply Last reply Reply Quote 1
                                  • ntoxicatorN
                                    ntoxicator
                                    last edited by

                                    We have a local data center down the road as well.. I've been wanting to negotiate shared rack space for power + BW as alternative backup area or for future hosting needs. That is separate topic for another day. Sure I'll get flamed for that one lol.

                                    JaredBuschJ 1 Reply Last reply Reply Quote 0
                                    • JaredBuschJ
                                      JaredBusch @ntoxicator
                                      last edited by

                                      @ntoxicator said:

                                      We have a local data center down the road as well.. I've been wanting to negotiate shared rack space for power + BW as alternative backup area or for future hosting needs. That is separate topic for another day. Sure I'll get flamed for that one lol.

                                      I'll flame it right here.. You don't negotiate for shared rack space. If they are truly a data center, then you rent collocation space. Negotiate your price point and bandwidth, sure. but it is a simple, clear concept.

                                      coliverC 1 Reply Last reply Reply Quote 2
                                      • coliverC
                                        coliver @JaredBusch
                                        last edited by

                                        @JaredBusch said:

                                        @ntoxicator said:

                                        We have a local data center down the road as well.. I've been wanting to negotiate shared rack space for power + BW as alternative backup area or for future hosting needs. That is separate topic for another day. Sure I'll get flamed for that one lol.

                                        I'll flame it right here.. You don't negotiate for shared rack space. If they are truly a data center, then you rent collocation space. Negotiate your price point and bandwidth, sure. but it is a simple, clear concept.

                                        Right if they are an enterprise class datacenter and sell collocation space then that's that... hell if you have a decent ISP or two you could relocate all of your stuff there... especially since you are already doing terminal services.

                                        J 1 Reply Last reply Reply Quote 0
                                        • ntoxicatorN
                                          ntoxicator
                                          last edited by

                                          Yes - I'm aware of colo'ing servers.

                                          Yes - i can negotiate or buy half rack or full rack for power and bw

                                          1 Reply Last reply Reply Quote 0
                                          • AconboyA
                                            Aconboy @ntoxicator
                                            last edited by

                                            @ntoxicator I will have Kevin Holmes and Ross Wimer reach out to you